Belden Point Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Belden Point on City Island Avenue.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2010
Projected Completion Date:
March 2012
Completion Date:
October 2012
Procurement
Start Date: October 2012
Projected Completion Date:
July 2013
Completion
Date:
March 2014
Construction
Start Date: March 2015
Projected Completion Date:
March 2016
Completion Date: December 2015
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- State
Location
City Island Avenue and Belden Street
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project