Aqueduct Walk Plaza Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the plaza, paths, and landscape in Aqueduct Walk.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2015
Projected Completion Date:
May 2016
Completion Date:
March 2017
Procurement
Start Date: March 2017
Projected Completion Date:
December 2017
Completion
Date:
July 2018
Construction
Start Date: October 2018
Projected Completion Date:
October 2019
Completion Date: October 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Aqueduct Walk, Bronx
Aqueduct Avenue between West 180th Street and West 181st Street
Community Board: 07
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks