Aqueduct Walk Plaza Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the plaza, paths, and landscape in Aqueduct Walk.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2015
Projected Completion Date: May 2016
Completion Date: March 2017

Procurement

Start Date: March 2017
Projected Completion Date: December 2017
Completion Date: July 2018

Construction

Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $2,832,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Aqueduct Walk, Bronx
Aqueduct Avenue between West 180th Street and West 181st Street
Community Board: 07

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025