Van Cortlandt Park Dog Run Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a dog run in Van Cortlandt Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2010
Projected Completion Date: May 2013
Completion Date: June 2016

Procurement

Start Date: June 2016
Projected Completion Date: March 2017
Completion Date: June 2017

Construction

Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $354,000
Funding Sources:
  • City Council
  • Mayoral

Location

Van Cortlandt Park, Bronx
Van Cortlandt Park East between Oneida Avenue and East 238th Street
Community Board: 07, 08, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024