Van Cortlandt Park Dog Run Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a dog run in Van Cortlandt Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2010
Projected Completion Date:
May 2013
Completion Date:
June 2016
Procurement
Start Date: June 2016
Projected Completion Date:
March 2017
Completion
Date:
June 2017
Construction
Start Date: August 2017
Projected Completion Date:
August 2018
Completion Date: June 2018
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Van Cortlandt Park, Bronx
Van Cortlandt Park East between Oneida Avenue and East 238th Street
Community Board: 07, 08, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024