Agnes Haywood Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Agnes Haywood Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2015
Projected Completion Date: February 2016
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: January 2017
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $3,498,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Agnes Haywood Playground, Bronx
Barnes Avenue between East 215th Street and East 216th Street
Community Board: 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024