Van Nest Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground at Van Nest Park, including new play equipment, a spray shower, sitting area and planting borders.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2011
Projected Completion Date:
November 2012
Completion Date:
February 2013
Procurement
Start Date: February 2013
Projected Completion Date:
October 2013
Completion
Date:
November 2013
Construction
Start Date: January 2014
Projected Completion Date:
January 2015
Completion Date: January 2015
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Van Nest Park, Bronx
Mead Street, White Plains Road, Unionport Avenue and Van Nest Avenue
Community Board: 11
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks