Freshkills North Park Pathway and Public Restroom Building Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a new multi-use pathway, overlook structures, and public restroom building with composting toilets in the northern section of Freshkills Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2012
Projected Completion Date:
March 2014
Completion Date:
March 2016
Procurement
Start Date: March 2016
Projected Completion Date:
December 2016
Completion
Date:
June 2017
Construction
Start Date: July 2017
Projected Completion Date:
January 2020
Completion Date: May 2022
Following construction completion, the New York State Department of Environmental Conservation must complete its certification of the site before it can be opened to the public. Therefore, the project site is expected to open to the public by Spring 2023.
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- State
Location
Freshkills Park, Staten Island
Dean Avenue, West Shore Expressway, Fresh Kills and Main Creek
Community Board: 02
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024