Laurelton West Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Laurelton West Playground located on 238th Street between 120th Avenue and 121st Avenue.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2009
Completion Date:
August 2011
Procurement
Start Date: August 2011
Projected Completion Date:
May 2012
Completion
Date:
March 2013
Construction
Start Date: June 2013
Projected Completion Date:
June 2014
Completion Date: June 2014
Understand how we build parks.
Funding
Funding Source: Borough President
Location
Laurelton Parkway, Queens
Project Staff
Project Liaison: Meira Berkower