Robert Clinkscales Playground and Community Garden Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct a playground and community garden at Robert Clinkscales Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2009
Completion Date:
October 2011
Procurement
Start Date: October 2011
Projected Completion Date:
July 2012
Completion
Date:
November 2012
Construction
Start Date: January 2013
Projected Completion Date:
January 2014
Completion Date: May 2014
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Private
Location
Robert L. Clinkscales Playground and Community Garden, Manhattan
Project Staff
Project Liaison: Steve Simon