Robert Clinkscales Playground and Community Garden Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct a playground and community garden at Robert Clinkscales Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2009
Completion Date: October 2011

Procurement

Start Date: October 2011
Projected Completion Date: July 2012
Completion Date: November 2012

Construction

Start Date: January 2013
Projected Completion Date: January 2014
Completion Date: May 2014

Understand how we build parks.

Funding

Total Funding: $1,106,000
Funding Sources:
  • City Council
  • Private

Location

Robert L. Clinkscales Playground and Community Garden, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024