Lincoln Terrace Park Tennis Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the tennis courts in Lincoln Terrace Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2010
Projected Completion Date:
February 2012
Completion Date:
March 2012
Procurement
Start Date: March 2012
Projected Completion Date:
December 2012
Completion
Date:
October 2012
Construction
Start Date: November 2012
Projected Completion Date:
November 2013
Completion Date: November 2013
Understand how we build parks.
Funding
Funding Source: City Council
Location
Lincoln Terrace / Arthur S. Somers Park, Brooklyn
Buffalo Avenue, East New York Avenue, Portal Street, Eastern Parkway
Community Board: 08
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024