Co-Op City Field Bleacher and Pathway Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the entrance area, fencing, bleachers, and pavements at Co-Op City Field.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2008
Projected Completion Date: February 2012
Completion Date: February 2012

Procurement

Start Date: February 2012
Projected Completion Date: November 2012
Completion Date: December 2012

Construction

Start Date: March 2013
Projected Completion Date: February 2014
Completion Date: August 2014

Understand how we build parks.

Funding

Total Funding: $329,000
Funding Source: Mayoral

Location

Co-op City Field, Bronx
Co-Op City Boulevard and the Hutchinson River
Community Board: 10

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024