Citywide Plumbing Systems Reconstruction (CNYG-1007M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the plumbing systems in public restroom buildings at various park facilities citywide.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2006
Completion Date:
March 2007
Procurement
Start Date: March 2007
Projected Completion Date:
November 2007
Completion
Date:
May 2008
Construction
Start Date: June 2008
Projected Completion Date:
June 2011
Completion Date: April 2014
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Locations
-
Alley Pond Park, Queens
Little Neck Bay to Springfield Boulevard, Union Turnpike
Community Board: 11 -
Bushwick Playground, Brooklyn
Knickerbocker Avenue between Woodbine Street and Putnam Avenue
Community Board: 04 -
Carver Playground, Brooklyn
Sumpter Street between Ralph Avenue and Howard Avenue
Community Board: 03 -
Fort Totten Park, Queens
Fort Totten, Cross Island Parkway, Totten Road to 15 Road
Community Board: 07 -
Hammel Playground, Queens
Beach 83rd Street & Rockaway Beach Boulevard
Community Board: 14 -
Highbridge Park, Manhattan
West 189th Street & Amsterdam Avenue
Community Board: 10, 12 -
Inwood Hill Park, Manhattan
Dyckman Street, Hudson River, Harlem River Ship Canal
Community Board: 12 -
Louis Armstrong Playground, Queens
37 Avenue between 112 & 113 Streets
Community Board: 03 -
Sixteen Sycamores Playground, Brooklyn
Schermerhorn & Nevins Street
Community Board: 02 -
Brooklyn - Queens Connecting Highway, Brooklyn
Middagh Street between Columbia Heights & Furman Street
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024