Citywide Buildings Reconstruction (CNYG-209M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct buildings and public restroom buildings in various parks citywide.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2009
Completion Date: September 2009

Procurement

Start Date: September 2009
Projected Completion Date: June 2010
Completion Date: July 2010

Construction

Start Date: July 2010
Projected Completion Date: July 2013
Completion Date: February 2015

Understand how we build parks.

Funding

Total Funding: $2,171,000
Funding Sources:
  • City Council
  • Mayoral

Locations

  • Bushwick Playground, Brooklyn
    Knickerbocker Avenue between Woodbine Street and Putnam Avenue
    Community Board: 04
  • Flushing Meadows Corona Park, Queens
    Grand Central Parkway, Van Wyck Expressway
    Community Board: 03, 04, 06, 07, 08
  • Gertrude Ederle Recreation Center, Manhattan
    West 59 Street, West 60 Street between Amsterdam Avenue and West End Avenue
    Community Board: 07
  • Haffen Park, Bronx
    Hammersley, Ely, Burke, Gunther Avenues
    Community Board: 12
  • Hammel Playground, Queens
    Beach 83rd Street & Rockaway Beach Boulevard
    Community Board: 14
  • Harris Park, Bronx
    Goulden Avenue, West 205 Street, Paul Avenue, Bedford Park Boulevard
    Community Board: 07
  • Highbridge Park, Manhattan
    West 155th & Dyckman Streets, Edgecombe & Amsterdam Avenues
    Community Board: 10, 12
  • Inwood Hill Park, Manhattan
    Dyckman Street, Hudson River, Harlem River Ship Canal
    Community Board: 12
  • Sixteen Sycamores Playground, Brooklyn
    Schermerhorn & Nevins Street
    Community Board: 02
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024