Citywide Electrical Systems Reconstruction (CNYG-907M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct electrical systems in various parks citywide.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2006
Completion Date: March 2007

Procurement

Start Date: March 2007
Projected Completion Date: November 2007
Completion Date: July 2008

Construction

Start Date: August 2008
Projected Completion Date: August 2011
Completion Date: October 2014

Understand how we build parks.

Funding

Total Funding: $1,330,000
Funding Sources:
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024