Greenbelt Native Plant Center Heating System Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the heating system at the Greenbelt Native Plant Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2009
Projected Completion Date:
July 2012
Completion Date:
November 2013
Procurement
Start Date: November 2013
Projected Completion Date:
August 2014
Completion
Date:
March 2015
Construction
Start Date: May 2015
Projected Completion Date:
May 2016
Completion Date: November 2016
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Greenbelt Native Plant Center, Staten Island
3808 Victory Boulevard
Community Board: 02
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024