Greenbelt Native Plant Center Heating System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the heating system at the Greenbelt Native Plant Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2009
Projected Completion Date: July 2012
Completion Date: November 2013

Procurement

Start Date: November 2013
Projected Completion Date: August 2014
Completion Date: March 2015

Construction

Start Date: May 2015
Projected Completion Date: May 2016
Completion Date: November 2016

Understand how we build parks.

Funding

Total Funding: $47,000
Funding Source: Mayoral

Location

Greenbelt Native Plant Center, Staten Island
3808 Victory Boulevard
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024