Stonehenge Boiler and Heating Systems Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the boiler and heating systems at Stonehenge in Clove Lakes Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2009
Completion Date: September 2010

Procurement

Start Date: September 2010
Projected Completion Date: May 2011
Completion Date: August 2011

Construction

Start Date: April 2012
Projected Completion Date: October 2012
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $155,000
Funding Source: Mayoral

Location

Clove Lakes Park, Staten Island
Clove Road between Cheshire Place and Fox Hunt Court
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/26/2024