New Springville Greenway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a 3.2 mile multi-use path running along the edges of Freshkills Park, William T. Davis Wildlife Refuge and La Tourette Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2009
Projected Completion Date: October 2012
Completion Date: October 2012

Procurement

Start Date: October 2012
Projected Completion Date: July 2013
Completion Date: December 2013

Construction

Start Date: January 2014
Projected Completion Date: July 2015
Completion Date: July 2015

Understand how we build parks.

Funding

Total Funding: $8,109,000
Funding Sources:
  • Federal
  • Mayoral

Locations

  • Freshkills Park, Staten Island
    Victory Boulevard, Signs Road, Travis Avenue, Arthur Kill Road
    Community Board: 02
  • LaTourette Park & Golf Course, Staten Island
    Forest Hill & London Roads, Rockland Avenue
    Community Board: 02, 03
 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024