New Springville Greenway Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a 3.2 mile multi-use path running along the edges of Freshkills Park, William T. Davis Wildlife Refuge and La Tourette Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2009
Projected Completion Date:
October 2012
Completion Date:
October 2012
Procurement
Start Date: October 2012
Projected Completion Date:
July 2013
Completion
Date:
December 2013
Construction
Start Date: January 2014
Projected Completion Date:
July 2015
Completion Date: July 2015
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Locations
-
Freshkills Park, Staten Island
Victory Boulevard, Signs Road, Travis Avenue, Arthur Kill Road
Community Board: 02 -
LaTourette Park & Golf Course, Staten Island
Forest Hill & London Roads, Rockland Avenue
Community Board: 02, 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024