Owl Hollow Fields Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct four soccer fields and a parking lot at Owl Hollow Fields.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2005
Projected Completion Date: January 2006
Completion Date: April 2006

Procurement

Start Date: April 2006
Projected Completion Date: January 2007
Completion Date: October 2006

Construction

Start Date: March 2008
Projected Completion Date: March 2009
Completion Date: July 2013

Understand how we build parks.

Funding

Total Funding: $16,175,000
Funding Sources:
  • City Council
  • Mayoral

Location

Freshkills Park, Staten Island
Arthur Kill Road near Arden Avenue
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024