Westerleigh Park Rain Garden Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a rain garden and erosion control in Westerleigh Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2010
Projected Completion Date: December 2012
Completion Date: July 2014

Procurement

Start Date: July 2014
Projected Completion Date: April 2015
Completion Date: July 2015

Construction

Start Date: September 2015
Projected Completion Date: September 2016
Completion Date: September 2016

Understand how we build parks.

Funding

Total Funding: $840,000
Funding Sources:
  • Borough President
  • City Council

Location

Westerleigh Park, Staten Island
Willard, Springfield, Neal Dow and Main Avenues, Staten Island
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/11/2024