Faber Park Skate Park Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a plaza-type skate park at Faber Park, including new drainage structures and trees.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2011
Projected Completion Date:
August 2012
Completion Date:
March 2013
Procurement
Start Date: March 2013
Projected Completion Date:
November 2013
Completion
Date:
November 2013
Construction
Start Date: January 2014
Projected Completion Date:
January 2015
Completion Date: January 2015
Understand how we build parks.
Funding
Funding Source: Borough President
Location
Faber Pool and Park, Staten Island
Faber Street and Sharpe Avenue
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024