Kissena Corridor Park Ballfield 5 Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct Ballfield 5 at Kissena Corridor Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2021
Projected Completion Date: April 2022
Completion Date: February 2023

Procurement

Start Date: February 2023
Projected Completion Date: February 2024
Adjusted Completion Date: October 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Location

Kissena Corridor Park, Queens
Underhill Avenue and Peck Avenue between Utopia Parkway and 50th Avenue.
Community Board: 08, 11

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024