Kissena Corridor Park Ballfield 5 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Ballfield 5 at Kissena Corridor Park.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2021
Projected Completion Date: April 2022
Completion Date: February 2023

Procurement

Start Date: February 2023
Projected Completion Date: February 2024
Completion Date: October 2024

Construction

Start Date: March 2025
Projected Completion Date: March 2026

Understand how we build parks.

Funding

Total Funding: $3,016,000
Funding Source: City Council

Location

Kissena Corridor Park, Queens
Underhill Avenue and Peck Avenue between Utopia Parkway and 50th Avenue.
Community Board: 08, 11

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025