Beach Channel (P.S. 183) Playground Reconstruction (Q403-111M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Beach Channel (P.S. 183) Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2010
Completion Date: February 2012

Procurement

Start Date: February 2012
Projected Completion Date: November 2012
Completion Date: March 2013

Construction

Start Date: April 2013
Projected Completion Date: March 2014
Completion Date: March 2014

Understand how we build parks.

Funding

Total Funding: $946,000
Funding Source: City Council

Location

Beach Channel Playground, Queens
Beach Channel Drive between Beach 79th Street & Beach 80th Street
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025