Beach Channel (P.S. 183) Playground Reconstruction (Q403-111M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Beach Channel (P.S. 183) Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2010
Completion Date:
February 2012
Procurement
Start Date: February 2012
Projected Completion Date:
November 2012
Completion
Date:
March 2013
Construction
Start Date: April 2013
Projected Completion Date:
March 2014
Completion Date: March 2014
Understand how we build parks.
Funding
Funding Source: City Council
Location
Beach Channel Playground, Queens
Beach Channel Drive between Beach 79th Street & Beach 80th Street
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025