Design
Assigned & Start Date: April 2009
Projected Completion Date:
January 2012
Completion Date:
January 2012
Procurement
Start Date: January 2012
Projected Completion Date:
October 2012
Completion
Date:
January 2013
Construction
Start Date: January 2013
Projected Completion Date:
January 2014
Completion Date: January 2014