Highland Park Perimeter Pathways, Fencing and Security Lighting Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the perimeter pathways, fencing, and security lighting around Ridgewood Reservoir in Highland Park
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2008
Projected Completion Date:
June 2009
Completion Date:
January 2010
Procurement
Start Date: January 2010
Projected Completion Date:
October 2010
Completion
Date:
March 2011
Construction
Start Date: May 2011
Projected Completion Date:
February 2012
Completion Date: September 2013
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Highland Park, Queens
Highland Boulevard, Vermont Place, Jackie Robinson Parkway.
Community Board: 05, 05
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024