Highland Park Perimeter Pathways, Fencing and Security Lighting Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the perimeter pathways, fencing, and security lighting around Ridgewood Reservoir in Highland Park

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2008
Projected Completion Date: June 2009
Completion Date: January 2010

Procurement

Start Date: January 2010
Projected Completion Date: October 2010
Completion Date: March 2011

Construction

Start Date: May 2011
Projected Completion Date: February 2012
Completion Date: September 2013

Understand how we build parks.

Funding

Total Funding: $6,737,000
Funding Source: Mayoral

Location

Highland Park, Queens
Highland Boulevard, Vermont Place, Jackie Robinson Parkway.
Community Board: 05, 05

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024