Queens General Site Work (QG-212M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct pavements, fencing, plantings and general site work in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2012
Projected Completion Date: November 2012
Completion Date: November 2013

Procurement

Start Date: November 2013
Projected Completion Date: August 2014
Completion Date: November 2014

Construction

Start Date: March 2015
Projected Completion Date: August 2016
Completion Date: October 2016

Understand how we build parks.

Funding

Total Funding: $546,000
Funding Sources:
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project