Queens General Site Work (QG-212M)
-
100% complete
-
100% complete
-
100% complete
This multisite contract will reconstruct pavements, fencing, plantings and general site work in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2012
Projected Completion Date:
November 2012
Completion Date:
November 2013
Procurement
Start Date: November 2013
Projected Completion Date:
August 2014
Completion
Date:
November 2014
Construction
Start Date: March 2015
Projected Completion Date:
August 2016
Completion Date: October 2016
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Locations
-
Flushing Meadows Corona Park, Queens
Grand Central Pkwy., Whitestone Exwy. bet. 111 St. and College Point Blvd., Park Drive E.
Community Board: 03, 04, 06, 07, 08 -
Roy Wilkins Recreation Center, Queens
Baisley & Merrick Boulevards, 115 Avenue
Community Board: 12 -
Yellowstone Park, Queens
Yellowstone Blvd. bet. 68 Ave. and 68 Rd.
Community Board: 06
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025