Flushing Meadows Corona Park Pavement and Fence Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct pavements and fences at the tennis courts and near the LIRR tracks in Flushing Meadows Corona Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2010
Completion Date: June 2011

Procurement

Start Date: June 2011
Projected Completion Date: March 2012
Completion Date: September 2012

Construction

Start Date: October 2012
Projected Completion Date: April 2014
Completion Date: September 2013

Understand how we build parks.

Funding

Total Funding: $750,000
Funding Source: Federal

Location

Flushing Meadows Corona Park, Queens
Grand Central Pkwy., Whitestone Exwy. bet. 111 St. and College Point Blvd., Park Drive E.
Community Board: 03, 04, 06, 07, 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/26/2024