Fort Totten Park Seawall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the seawall in Fort Totten Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2009
Completion Date: May 2012

Procurement

Start Date: May 2012
Projected Completion Date: February 2013
Completion Date: July 2013

Construction

Start Date: August 2013
Projected Completion Date: August 2014
Completion Date: August 2014

Understand how we build parks.

Funding

Total Funding: $1,191,000
Funding Source: Mayoral

Location

Fort Totten Park, Queens
Cross Island Parkway, Totten Road, Long Island Sound
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project