Queens General Site Work (QG-811M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct play equipment, safety surfacing, pavements, fencing, tennis courts, handball courts and plantings at various parks in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2011
Completion Date: April 2011

Procurement

Start Date: April 2011
Projected Completion Date: December 2011
Completion Date: January 2012

Construction

Start Date: March 2012
Projected Completion Date: September 2013
Completion Date: September 2013

Understand how we build parks.

Funding

Total Funding: $1,513,000
Funding Sources:
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024