Queens General Site Work (QG-811M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct play equipment, safety surfacing, pavements, fencing, tennis courts, handball courts and plantings at various parks in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2011
Completion Date:
April 2011
Procurement
Start Date: April 2011
Projected Completion Date:
December 2011
Completion
Date:
January 2012
Construction
Start Date: March 2012
Projected Completion Date:
September 2013
Completion Date: September 2013
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Locations
-
Hempstead Bench Spread, Queens
104 Ave. bet. 225 St. and 227 St.
Community Board: 13 -
Hermon A. MacNeil Park, Queens
Poppenhusen Ave. bet. 115 St. and College Pl.
Community Board: 07 -
Kissena Park, Queens
Fresh Meadows La., Kissena Blvd., bet. Oak Ave., Underhill., and Booth Memorial Ave.
Community Board: 07 -
Locust Grove Civic Triangle, Queens
N Conduit Av bet 118 St & Lefferts Blvd
Community Board: 10 -
South Rochdale Playground, Queens
173 St and 137 Av
Community Board: 12
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024