Queens General Site Work (QG-711M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct pavements, fencing, tennis courts, handball courts and plantings at various parks in Queens.
Project Timeline
Design
Assigned & Start Date: February 2011
Completion Date:
April 2011
Procurement
Start Date: April 2011
Projected Completion Date:
January 2012
Completion
Date:
December 2011
Construction
Start Date: February 2012
Projected Completion Date:
August 2013
Completion Date: August 2013
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Locations
-
Alley Athletic Playground, Queens
Grand Central Parkway, Union Turnpike, Winchester Boulevard
Community Board: 13 -
Cunningham Park, Queens
LIE., 73 Ave., Union Turnpike, GCP bet. 193 St., Francis Lewis Blvd., Hollis Hills Ter., and 210 St.
Community Board: 08 -
Rockaway Beach Boardwalk, Queens
Beach 73rd to Beach 109th Streets
Community Board: 14 -
Roy Wilkins Recreation Center, Queens
Baisley & Merrick Boulevards, 115 Avenue
Community Board: 12