Queens General Site Work (QG-711M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct pavements, fencing, tennis courts, handball courts and plantings at various parks in Queens.

Project Timeline

Design

Assigned & Start Date: February 2011
Completion Date: April 2011

Procurement

Start Date: April 2011
Projected Completion Date: January 2012
Completion Date: December 2011

Construction

Start Date: February 2012
Projected Completion Date: August 2013
Completion Date: August 2013

Understand how we build parks.

Funding

Total Funding: $1,890,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024