Louis Armstrong Center HVAC Center Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the HVAC system at the Louis Armstrong Community Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2007
Projected Completion Date:
April 2009
Completion Date:
March 2010
Procurement
Start Date: March 2010
Projected Completion Date:
December 2010
Completion
Date:
June 2011
Construction
Start Date: September 2011
Projected Completion Date:
September 2012
Completion Date: August 2013