Louis Armstrong Center HVAC Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the HVAC system at the Louis Armstrong Community Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2007
Projected Completion Date: April 2009
Completion Date: March 2010

Procurement

Start Date: March 2010
Projected Completion Date: December 2010
Completion Date: June 2011

Construction

Start Date: September 2011
Projected Completion Date: September 2012
Completion Date: August 2013

Understand how we build parks.

Funding

Total Funding: $2,833,000
Funding Source: Borough President

Location

Louis Armstrong Community Center, Queens
33-16 108th Street
Community Board: 03

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project