Rockaway Beach Skate Park Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the skate park at Rockaway Beach.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2015
Projected Completion Date:
April 2016
Completion Date:
January 2018
Procurement
Start Date: January 2018
Projected Completion Date:
October 2018
Completion
Date:
July 2019
Construction
Start Date: September 2019
Projected Completion Date:
December 2020
Completion Date: October 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Federal
- Mayoral
Location
Rockaway Beach Boardwalk, Queens
Shore Front Parkway between Beach 91st Street and Beach 92nd Street
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025