Rockaway Beach Skate Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the skate park at Rockaway Beach.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2015
Projected Completion Date: April 2016
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: July 2019

Construction

Start Date: September 2019
Projected Completion Date: December 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $3,457,000
Funding Sources:
  • Borough President
  • Federal
  • Mayoral

Location

Rockaway Beach Boardwalk, Queens
Shore Front Parkway between Beach 91st Street and Beach 92nd Street
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project