Lanett Playground Reconstruction and Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and construct a new public restroom building at PS 197 (Lanett) Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2009
Projected Completion Date: January 2011
Completion Date: January 2011

Procurement

Start Date: January 2011
Projected Completion Date: October 2011
Completion Date: March 2012

Construction

Start Date: April 2012
Projected Completion Date: April 2014
Completion Date: April 2014

Understand how we build parks.

Funding

Total Funding: $2,078,000
Funding Sources:
  • Borough President
  • City Council
  • State

Location

Lanett Playground, Queens
Lanett Ave. bet. Beach 9 St. and Beach 8 St.
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024