Idlewild Park Nature Center Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a nature center in Idlewild Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2010
Projected Completion Date: June 2013
Completion Date: October 2016

Procurement

Start Date: October 2016
Projected Completion Date: July 2017
Completion Date: May 2018

Construction

Start Date: September 2018
Projected Completion Date: February 2020
Completion Date: August 2021

Understand how we build parks.

Funding

Total Funding: $7,789,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Idlewild Park, Queens
149th Avenue and Springfield Lane
Community Board: 13

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025