Rufus King Park Gazebo Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the gazebo and construct new pathways in Rufus King Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2011
Projected Completion Date: June 2013
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: August 2014
Completion Date: January 2015

Construction

Start Date: March 2015
Projected Completion Date: March 2016
Completion Date: November 2016

Understand how we build parks.

Funding

Total Funding: $1,706,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Rufus King Park, Queens
150th Street, 153rd Street, Jamaica Avenue, 84th Avenue
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025