Alley Pond Park Paths and Drainage Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the paths and address drainage issues at Oakland Lake in Alley Pond Park.
Project Timeline
Design
Assigned & Start Date: March 2011
Projected Completion Date:
October 2013
Completion Date:
November 2013
Procurement
Start Date: November 2013
Projected Completion Date:
August 2014
Completion
Date:
July 2014
Construction
Start Date: September 2014
Projected Completion Date:
September 2015
Completion Date: August 2015
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Alley Pond Park, Queens
46th Avenue between Springfield Boulevard and Cloverdale Boulevard
Community Board: 11