This project will reconstruct the paths and address drainage issues at Oakland Lake in Alley Pond Park.

Project Timeline

Design

Assigned & Start Date: March 2011
Projected Completion Date: October 2013
Completion Date: November 2013

Procurement

Start Date: November 2013
Projected Completion Date: August 2014
Completion Date: July 2014

Construction

Start Date: September 2014
Projected Completion Date: September 2015
Completion Date: August 2015

Understand how we build parks.

Funding

Total Funding: $1,288,000
Funding Sources:
  • Borough President
  • City Council

Location

Alley Pond Park, Queens
46th Avenue between Springfield Boulevard and Cloverdale Boulevard
Community Board: 11

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project