Alley Pond Environmental Center Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will construct a new environmental center in Alley Pond Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2010
Projected Completion Date:
July 2013
Completion Date:
August 2017
Procurement
Start Date: August 2017
Projected Completion Date:
May 2018
Completion
Date:
July 2019
Construction
Start Date: September 2019
Projected Completion Date:
September 2021
Completion Date: September 2023
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Alley Pond Park, Queens
Northern Boulevard and Cross Island Parkway
Community Board: 11