Cunningham Park Ballfields 2-4 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct ballfields 2, 3 and 4 in Cunningham Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2008
Projected Completion Date: June 2009
Completion Date: May 2011

Procurement

Start Date: May 2011
Projected Completion Date: February 2012
Completion Date: May 2012

Construction

Start Date: July 2012
Projected Completion Date: July 2013
Completion Date: July 2013

Understand how we build parks.

Funding

Total Funding: $1,461,000
Funding Sources:
  • Borough President
  • City Council

Location

Cunningham Park, Queens
Near Union Turnpike and 193rd Street.
Community Board: 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024