Memorial Field of Flushing Ballfield Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the ballfield closest to 25th Avenue in Memorial Field of Flushing.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2009
Projected Completion Date: May 2010
Completion Date: September 2010

Procurement

Start Date: September 2010
Projected Completion Date: June 2011
Completion Date: April 2012

Construction

Start Date: June 2012
Projected Completion Date: November 2013
Completion Date: October 2013

Understand how we build parks.

Funding

Total Funding: $690,000
Funding Source: Borough President

Location

Flushing Fields, Queens
25th Avenue between 149th and 150th Streets
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024