Memorial Field of Flushing Ballfield Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the ballfield closest to 25th Avenue in Memorial Field of Flushing.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2009
Projected Completion Date:
May 2010
Completion Date:
September 2010
Procurement
Start Date: September 2010
Projected Completion Date:
June 2011
Completion
Date:
April 2012
Construction
Start Date: June 2012
Projected Completion Date:
November 2013
Completion Date: October 2013
Understand how we build parks.
Funding
Funding Source: Borough President
Location
Flushing Fields, Queens
25th Avenue between 149th and 150th Streets
Community Board: 07
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024