Bowne Park Bocce Court Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a bocce court in Bowne Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2011
Projected Completion Date: January 2012
Completion Date: February 2012

Procurement

Start Date: February 2012
Projected Completion Date: October 2012
Completion Date: September 2012

Construction

Start Date: October 2012
Projected Completion Date: October 2013
Completion Date: August 2013

Understand how we build parks.

Funding

Total Funding: $210,000
Funding Sources:
  • City Council
  • State

Location

Bowne Park, Queens
29th Avenue and 158th Street
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project