Bowne Park Bocce Court Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a bocce court in Bowne Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2011
Projected Completion Date:
January 2012
Completion Date:
February 2012
Procurement
Start Date: February 2012
Projected Completion Date:
October 2012
Completion
Date:
September 2012
Construction
Start Date: October 2012
Projected Completion Date:
October 2013
Completion Date: August 2013
Understand how we build parks.
Funding
Funding Sources:
- City Council
- State
Location
Bowne Park, Queens
29th Avenue and 158th Street
Community Board: 07
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024