Captain Tilly Park Landscape and Drainage Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the landscaped areas and drainage structures at Captain Tilly Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2010
Projected Completion Date:
May 2013
Completion Date:
November 2013
Procurement
Start Date: November 2013
Projected Completion Date:
August 2014
Completion
Date:
October 2014
Construction
Start Date: November 2014
Projected Completion Date:
November 2015
Completion Date: November 2015
Understand how we build parks.
Funding
Funding Source: City Council
Location
Captain Tilly Park, Queens
Highland Avenue, Upland Parkway, Gothic Parkway, 85th Avenue
Community Board: 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024