Frank Principe Park Ballfields Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a synthetic turf soccer field and reconstruct two ballfields with synthetic turf in Frank Principe Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2015
Projected Completion Date: May 2016
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: October 2017

Construction

Start Date: November 2017
Projected Completion Date: January 2019
Completion Date: November 2018

Understand how we build parks.

Funding

Total Funding: $5,225,000
Funding Source: City Council

Location

Frank Principe Park, Queens
63rd Street, 54th Avenue, Maurice Avenue, and Borden Avenue
Community Board: 05

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024