Juniper Valley Park Bocce Court Construction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct and expand the bocce court area in Juniper Valley Park with an additional bocce court, shade canopies, a sitting area, benches, and trees.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2011
Projected Completion Date:
January 2012
Completion Date:
November 2012
Procurement
Start Date: November 2012
Projected Completion Date:
August 2013
Completion
Date:
June 2013
Construction
Start Date: September 2013
Projected Completion Date:
September 2014
Completion Date: September 2014
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Juniper Valley Park, Queens
Juniper Boulevard North between 78th Street and 80th Street
Community Board: 05
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project