Juniper Valley Park Bocce Court Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct and expand the bocce court area in Juniper Valley Park with an additional bocce court, shade canopies, a sitting area, benches, and trees.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2011
Projected Completion Date: January 2012
Completion Date: November 2012

Procurement

Start Date: November 2012
Projected Completion Date: August 2013
Completion Date: June 2013

Construction

Start Date: September 2013
Projected Completion Date: September 2014
Completion Date: September 2014

Understand how we build parks.

Funding

Total Funding: $649,000
Funding Sources:
  • Borough President
  • City Council

Location

Juniper Valley Park, Queens
Juniper Boulevard North between 78th Street and 80th Street
Community Board: 05

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024