Noonan Playground Spray Shower and Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct a portion of the playground, improving safety within the park and providing definitive circulation for park users. A new spray shower and new play equipment will provide recreation for a wide range of children. The project will also extend the green space, mitigate drainage issues and enhance the main entrance of the park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2011
Projected Completion Date:
December 2012
Completion Date:
January 2013
Procurement
Start Date: January 2013
Projected Completion Date:
October 2013
Completion
Date:
March 2014
Construction
Start Date: April 2014
Projected Completion Date:
April 2015
Completion Date: March 2015
Understand how we build parks.
Funding
Funding Source: City Council
Location
L/CPL Thomas P. Noonan Jr. Playground, Queens
47th Avenue, 43rd Street, Greenpoint Avenue, 42nd Street
Community Board: 02
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024