Project Timeline
Design
Assigned & Start Date: June 2010
Projected Completion Date:
December 2010
Completion Date:
January 2011
Procurement
Start Date: January 2011
Projected Completion Date:
October 2011
Completion
Date:
November 2011
Construction
Start Date: March 2012
Projected Completion Date:
March 2013
Completion Date: December 2013