Athens Square Playground Plaza Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the plaza and adjacent seating area in Athens Square Playground. The cheek walls on either side of the two ramps will be reconstructed and a new ramp will be constructed between the seating area and the plaza. New handrails will be installed, 2 1/2 foot fencing will be placed around plant beds, plant material will be replaced as needed, and a trench drain will be installed near the spray shower to keep water from flowing onto the safety surface.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2011
Completion Date:
January 2012
Procurement
Start Date: January 2012
Projected Completion Date:
October 2012
Completion
Date:
November 2012
Construction
Start Date: July 2013
Projected Completion Date:
July 2014
Completion Date: August 2014
Understand how we build parks.
Funding
Funding Source: Borough President
Location
Athens Square, Queens
30th Street and 30th Avenue, Queens
Community Board: 01
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024