Flushing Meadows Corona Park Fields 2,3,5 Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct synthetic turf fields 2, 3, and 5 in Flushing Meadows Corona Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2010
Projected Completion Date:
March 2011
Completion Date:
May 2011
Procurement
Start Date: May 2011
Projected Completion Date:
February 2012
Completion
Date:
April 2012
Construction
Start Date: June 2012
Projected Completion Date:
June 2013
Completion Date: July 2013
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Flushing Meadows Corona Park, Queens
Near Fountain of the Fairs
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025