Manhattan Roofing Systems Reconstruction (MG-709M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct roofs at various facilities in Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2008
Completion Date: March 2009

Procurement

Start Date: March 2009
Projected Completion Date: December 2009
Completion Date: December 2009

Construction

Start Date: January 2010
Projected Completion Date: January 2013
Completion Date: August 2015

Understand how we build parks.

Funding

Total Funding: $3,043,000
Funding Sources:
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024