Fort Washington Park Ballfields Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the ballfields in Fort Washington Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2010
Projected Completion Date: August 2011
Completion Date: January 2012

Procurement

Start Date: January 2012
Projected Completion Date: October 2012
Completion Date: August 2012

Construction

Start Date: September 2012
Projected Completion Date: September 2013
Completion Date: October 2013

Understand how we build parks.

Funding

Total Funding: $2,672,000
Funding Source: Mayoral

Location

Fort Washington Park, Manhattan
Between West 164th Street and West 167th Street.
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024