Fort Washington Park Greenway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new waterfront mixed-use path in Fort Washington Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2009
Projected Completion Date: January 2011
Completion Date: January 2011

Procurement

Start Date: January 2011
Projected Completion Date: October 2011
Completion Date: April 2012

Construction

Start Date: June 2012
Projected Completion Date: June 2013
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $3,051,000
Funding Sources:
  • Federal
  • Mayoral

Location

Fort Washington Park, Manhattan
Between Dyckman Street and West 188th Street
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024