Battery Park Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct and expand the playground at The Battery.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2015
Projected Completion Date:
October 2017
Completion Date:
March 2019
Procurement
Start Date: March 2019
Projected Completion Date:
December 2019
Completion
Date:
November 2019
Construction
Start Date: December 2019
Projected Completion Date:
March 2021
Completion Date: December 2021
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Federal
- Private
Location
The Battery, Manhattan
State Street and Peter Minuit Plaza
Community Board: 01
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024