Battery Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct and expand the playground at The Battery.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2015
Projected Completion Date: October 2017
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: December 2019
Completion Date: November 2019

Construction

Start Date: December 2019
Projected Completion Date: March 2021
Completion Date: December 2021

Understand how we build parks.

Funding

Total Funding: $17,155,000
Funding Sources:
  • Borough President
  • City Council
  • Federal
  • Private

Location

The Battery, Manhattan
State Street and Peter Minuit Plaza
Community Board: 01

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024