J. Hood Wright Park Recreation Center HVAC Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the HVAC system at the recreation center in J. Hood Wright Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2010
Projected Completion Date:
October 2010
Completion Date:
December 2010
Procurement
Start Date: December 2010
Projected Completion Date:
September 2011
Completion
Date:
August 2011
Construction
Start Date: January 2012
Projected Completion Date:
January 2013
Completion Date: June 2014
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
J. Hood Wright Park, Manhattan
Fort Washington Avenue between West 174th and 175th Streets
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025