J. Hood Wright Park Recreation Center HVAC Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the HVAC system at the recreation center in J. Hood Wright Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2010
Projected Completion Date: October 2010
Completion Date: December 2010

Procurement

Start Date: December 2010
Projected Completion Date: September 2011
Completion Date: August 2011

Construction

Start Date: January 2012
Projected Completion Date: January 2013
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $737,000
Funding Sources:
  • Borough President
  • City Council

Location

J. Hood Wright Park, Manhattan
Fort Washington Avenue between West 174th and 175th Streets
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025